Budimex works divided into 4 stages. Builds including taxiways, aprons modernizes. There will also be renovated main runway.

Airport is being rebuilt. The project will cost more than 100 million zł. Work is expected to be completed within one year.

Reconstruction of the airport began in March. The main contractor is Warsaw Budimex that for previous work at the airport has already received 87 million zł. Value of the next phase of the project will exceed 100 million zł.

- As part of the order will be completely rebuilt infrastructure for the safe handling of air traffic - says Krzysztof Domagalski, the Airport Goleniów.

Yesterday we did reconnaissance after construction. Contractor commits an investment at all times an active airport. This makes it difficult task, but thanks to the passengers do not feel the burden associated with the work.

Budimex work divided into four stages. The first involves the construction of taxiways and the expansion of one of the aprons. Will also be renovated paved runway surface.

In the second stage, the contractor will build further stretch parallel taxiway and apron modernize another. By October, work should be completed. At that time there will be no restrictions in the operation of the airport.

In the next phase, a continuation of the taxiway and apron will be refurbished 1. By November, the company should be with these robots despatch. The last step consists of a major overhaul of the runway with a length of 2.5 kilometers and a width of 60 meters. Final work is planned in June next year.

- At this time, the airport is designated replacement runway, so the airport will continue to operate safely - adds Krzysztof Domagalski.
At the moment, Budimex took more than 35 percent. work.
Reconstruction of the airport is financed by an investment loan with PKO BP zł amount of 51.6 million, nearly 47.5 million zł EU funds and the money shareholders airport.

Source: GS24.pl